Ba Ria-Vung Tau Urban Sewerage and Development One Member Limited Company (BUSADCO) has held a meeting to report Mr. Nguyen Van Trinh, Chairman of the PPC some difficulties and obstacles which need to be solved on compensation, land clearance of Vung Tau wastewater collection, treatment and drainage pr. Vung Tau. Also attending the meeting, there were representatives of the Department of Natural Resources and Environment and the PC of Vung Tau city.
Up to now, the PC of Vung Tau City has issued the decision on compensation for 232/266 households regarding Vung Tau wastewater collection, treatment and drainage project. There were 214 households has accepted the compensation and handed over the land, 18 households has not received the compensation and handed over the land, 32 households and units still have no decision on approving the compensation. In order that the project can come into operation, Busadco requested the PC of Vung Tau City to early hand over 771,2m2 of VSCB represented by Mr. Le An in the area of Ward 8 and 06 households in the area of Thang Tam ward, Vung Tau City.
Speaking at the meeting, Mr. Nguyen Van Trinh, the Chairman of PPC directed the Department of Natural Resources and Environment to coordinate with departments and agencies to consult the PPC on reviewing and proposing solutions for the problems mentioned by Busadco.